Downtown Clarksburg road project extended after ‘large void’ found under intersection

Summary by WBOY
CLARKSBURG, W.Va. (WBOY) — The Clarksburg Water Board (CWB) provided updates on projects happening across the city on Tuesday, and one area has required "extensive extra work" and added traffic delays. The CWB said that while working on the project at the intersection of W. Pike and Milford Streets near Wendy's last week, the Clarksburg Public Works Department "discovered a large void under the intersection." One direction of the intersection wa…