GMS Project Update: Contractor completes geothermal test well

Summary by thecantoncitizen.com
Update: Contractor completes geothermal test well at GMS Kristy Lyons of Consigli, the construction firm overseeing construction of the new Galvin Middle School, reported that geothermal testing is going well and according to plan. The test well was drilled on Thursday, December 26, and completed about midday on Friday when the 800-foot depth was reached. The U-bend (pipe) was then installed on Friday afternoon, December 27. This week’s activiti…